Grange Lakes Corridor shared use path

We've been constructing a shared use path for pedestrians and cyclists between the lake in West Lakes and the River Torrens outfall channel.

The project aligns paths through open space areas next to the Grange Lakes drainage channel, along the creek next to Kirkcaldy Reserve, through linear reserves near Cudmore Terrace and next to the Henley & Grange Memorial Oval before winding its way through local streets to the River Torrens.

This corridor is mentioned in several of our strategic documents, including the Open Space Strategy, the Strategy for Walking & Cycling and the Corporate Plan.

The shared paths are 2.5 metres wide. This makes them a safe, accessible, all-weather off-road route for cyclists, school children, parents with prams and the mobility impaired.

We've upgraded the paths with public lighting, safety barrier fencing and new crossings over streets.

Stage 1 and 2
Between Trimmer Parade and Grange Railway line, were completed in 2014/15.
Concept Plan - Stages 1 and 2

Stage 3
Between Grange Railway Line and Jetty Street was completed in 2015/16.
Concept Plan - Stage 3

Stage 4A
Section alongside Napier Drive was completed in 2020.
Concept Plan - Stage 4

Stage 4B
Construction of a 2.5 metre wide reinforced concrete path, viewing deck, seating, retaining wall and public lighting in the section between Napier Drive and Jetty Street (alongside The Grange - the former home of Captain Charles Sturt) was completed in October 2023.
Concept Plan - Stage 4B

Stage 5
Construction works through Kirkcaldy Park (between Beach Street and Grange Road) were completed in 2016/17. These works involved replacement of the existing 1.2 metre wide path with a 2.5 metre wide reinforced concrete path, construction of new fencing and installation of new LED public lighting.
Concept Plan - Stage 5

Stage 6
Construction works through Colin Sellars Reserve (between Grange Road and Marlborough Street) were completed in 2017/18. These works involved construction of a new 2.5 metre wide reinforced concrete path and installation of new LED public lighting and planting of new trees.
Concept Plan - Stage 6

Future Stages
Stage 7 - Marlborough Street to North Street (through Don Ferguson Reserve) is currently in detailed design phase with consultation planned for late 2023.
Stage 8 - North Street to Atkin Street (through Chambers Reserve & Henley & Grange Memorial Reserve) is currently in detailed design phase with consultation planned for late 2023.
Stage 9 - Atkin Street to Henley Beach Road along Cudmore Terrace is planned for construction in late 2023/early 2024 with expected completion of March 2024.


First round of consultation for these stages has occurred.
More information

Stages 10 -12 are yet to be determined and is subject to future budget allocation.

More information